Industry news

Vietnam plans 292 transmission projects by 2030: what it means for substation commissioning

Vietnam is preparing one of the largest transmission build-outs in Southeast Asia. Under the revised Power Development Plan VIII (PDP VIII), Vietnam Electricity (EVN) and its transmission arm, the National Power Transmission Corporation (EVNNPT), are responsible for 292 transmission projects between 2026 and 2030, according to Power Line (August 2026).

The programme in numbers

Item2026–2030
Transmission projects292 (78 at 500 kV, 214 at 220 kV)
Transmission linesabout 16,665 km
Transformer capacity91,263 MVA
Estimated investmentVND 157.9 trillion

Funding is a challenge. At a forum organised by the Ministry of Industry and Trade and the Vietnam Energy Association in August 2025, total capital demand for grid investment in 2025–2030 was put at about US$18.1 billion. EVN's own funding capacity for 2026–2030, about VND 180.75 trillion, covers only around 40 % of what PDP VIII requires, so social and private capital is expected to play a larger part (SGGP).

What 91,000 MVA of new transformers means

Every 500 kV and 220 kV substation in the programme brings power transformers, circuit breakers, instrument transformers and protection that must be tested before energisation. With almost 300 projects in five years, many substations will be commissioned in parallel by EVNNPT teams, provincial power companies and EPC contractors.

A typical commissioning scope for each new substation includes:

HUAC-JS-1000 automatic tan delta and capacitance tester
Tan delta and capacitance tests are part of every transformer and bushing commissioning scope. HUAC-JS-1000

Why test equipment planning matters now

When dozens of substations are commissioned in the same year, test sets become a bottleneck in their own right. Contractors that plan their instrument fleet early, standardise on equipment their teams already know and keep reports in the format EVNNPT expects will move faster from energisation to handover. Battery-powered and lightweight instruments also help on remote line and substation sites with limited auxiliary supply.

HUAC supplies transformer, switchgear, CT/VT, relay and high-voltage test equipment to utilities and contractors in Vietnam and across Southeast Asia. Send us your substation scope and we will propose a commissioning test set.

Sources

  • Power Line, "Vietnam's EVNNPT to complete 292 projects under revised PDP VIII", 17 August 2026.
  • SGGP, "Total capital demand for grid investment in 2025–2030 exceeds US$18 billion", 15 August 2025.
WhatsApp Get a quote
WhatsApp